The original item was published from August 6, 2025 2:03 PM to October 7, 2025 12:05 AM
The City of Geneva will be replacing a water main near the Northwestern Medicine Delnor Hospital Health & Fitness Center. See the construction web page for a project map and more information.
Aug. 6 Update
After a few delays with locating utilities and other schedule conflicts, the contractor is expected to start construction the week of Aug. 11.
Fitness Center access will remain available during the project, though visitors should be mindful of contractors and operating equipment.
While the main driving lane in the Fitness Center parking lot will be open, other drive aisles may be temporarily closed. Certain sections of the parking lot may be blocked off to accommodate construction.
Work is now anticipated to be substantially complete by mid-September, with the full project wrapping up later that month, weather permitting.