The City's 2023 sidewalk and curb maintenance program is scheduled for Monday to Friday, June 26-30, followed by a five-day curing period that will run into July. The schedule is weather-dependent.
The City's contractor, Globe Construction, will generally be working southwest to northeast during the week. Crews will be removing the old sidewalk, setting forms, pouring concrete, and then smoothing out the new surface. Sidewalk sections and curbs scheduled for replacement have been marked with white paint and can be found on the City's project map.
Notices were mailed to adjacent households in mid-June, including those residents who will have to park their cars on the street given that their driveways will be impacted by construction.
For more information, contact the City Engineer Brian Davids by calling 630-232-1501 or sending him an emaill.