Street Improvement Program - Sept. 15 Update

City Road Construction

The City is working with Geneva Construction on 23 road resurfacing and drainage projects included in the 2023 street improvement program, which started in August and is expected to be completed in October. Here is the Sept. 15 update:

Completed Work

Since the last update, the City's contractor has finished:

Replacing Concrete, Milling and Repaving of:

  • Fifth Street from State (Route 38) to Stevens streets; 
  • Third Street from Hamilton to Stevens streets;  and
  • Crawford & Eighth streets.

Concrete Replacement, Milling, and Binder:

  • Wakefield Lane from Williamsburg Avenue to Bloomfield Circle (including Paddock Court); and
  • Williamsburg Avenue from Randall Road to about Andover Lane.

Concrete Replacement (sidewalk and curb)

  • Williamsburg Avenue from State Street to Andover Lane; and
  • Lark Court.

Ongoing Projects

Work on the underground storm sewer projects on Ridge, Briar and Valley lanes will continue into next week.

What Is On Deck

Projects that will get underway the week of Sept. 18 will be:

Repaving/Final Surface

  • Mead Court; and
  • Wakefield Lane from Williamsburg Avenue to Bloomfield Circle (including Paddock Court).

Milling & Binder

  • Williamsburg Avenue from about Andover Lane to State Street.

Construction is weather-dependent and subject to change.